In line with our expansion strategy DCAM is in full preparation for the development of a new 35,000 m2 warehouse facility in the Roosendaal Borchwerf II park. Construction works are scheduled to start this autumn.

With Engineering in the final stage we are still able to optimise the design of this
energy efficient facility, to make its characteristics seamlessly aligned with the needs of the future occupier.

DCAM secured the land plot and will aim to
commence the construction of this facility in Q3’16.
Completion of the facility is scheduled to take place at the end of the first quarter of 2017. During the final 2 last months of construction we offer the possibility for early access and allow the future tenant to organise the fit-out of the facility before the actual lease term kick in.